Saturday, December 17, 2011

Create the Timeline View in Microsoft Project 2010

Detailed project schedules are great, but when it comes to communicating major milestones, phases, or tollgates to customers, executives, and even the project team, simplicity is key. Despite all the project management systems, spreadsheets, and templates available to project managers, it is still easier to communicate a project timeline with pictures.
Experienced project managers are familiar with the concept of a simple milestone chart or a high-level Gantt chart that depicts the project timeline. Prior to Microsoft Project 2010, I always created a milestone chart using Microsoft PowerPoint or a drawing tool such as Microsoft Visio. Developing a milestone chart in PowerPoint or Visio is an administrative challenge because each milestone needs to be adjusted and tweaked as the project schedule changes. I would waste a good hour moving milestone icons, adjusting dates, and changing the text to properly fit the custom milestone chart. Now I save myself a lot of hassle by using the Microsoft Project 2010 Timeline View


The Timeline View provides an overview of the project schedule and lets you select only the tasks and milestones that need to be communicated. This is very different from filtering the Gantt chart to display only the milestones and the summary tasks. I can pick any summary task, milestone, or individual task and depict it in the Timeline View. Since the view is automatically created based on the project data, any changes in the dates are immediately reflected in the Timeline View. I save a lot of time and develop a meaningful chart based on changing project schedule data.
In Figure A, I color-coded the specific phases based on the respective project teams. I can also color-code the milestones or individual tasks to reflect complete, on schedule, at risk, or late milestones. Tasks can be depicted as bars in the view or as individual call outs. Adding and removing tasks is simple, and the entire view can be copied and pasted into an email or status report.

Creating the Timeline View

Follow these steps to create the Timeline View:
1. Select the View tab.
2. Click the Timeline checkbox. A blank timeline window will appear






3. Find a milestone in your project schedule.
4. Right-click the task and select Add to Timeline



5. The milestone will appear on the Timeline View.
Repeat this five-step process for summary tasks, individual tasks, or groups of tasks.
When all the necessary tasks have been added to the Timeline View, you can use the Format menu to color-code the bars or change the way the tasks are displayed


You can also insert new tasks or milestones directly into the Timeline View.

Related Links:-
How To Fix Error Crypt32.dll in MS Office
How To Fix office 2010 msxml error
How to Repair Error 1719 office 2010





Source:-http://www.techrepublic.com/blog/tech-manager/create-the-timeline-view-in-microsoft-project-2010/5245

2 comments:

to know how to add constraint to your tasks see
Add constraint in MSP

I don't know what the best way to show a project timeline is - all I know is that it's the best thing to do to make sure a project gets done haha.